The power flow: the Crimea began to supply electricity to the Kuban

Переток мощности: Крым начал поставлять электроэнергию на Кубань

In the Crimea completed comprehensive testing of the second unit of the Tauride TPP. The power system is operated with an excess of their own generation and provide the results to the Kuban up to 300 MW of capacity. About it reports a press-service of the Ministry of energy.

“In the Crimea completed comprehensive testing of the second unit of the Taurian TPP. The unit worked continuously with rated load for 72 hours. In the context of work already commissioned two units of Balaklava thermal power plant and the first unit of thermal power plant Taurian, Crimean power system operated with an excess of their own generation and provided results in the Kuban energy system up to 300 MW,” – said the Agency.

The Ministry said that the power flow has taken place in some hours of the night, at times of low consumption.

It is noted that during the test block specialists ensured the stable operation of the Crimean energy system. “The preparation for testing and commissioning the new generating equipment Tauride TPP calculations of electric modes of the Crimean energy system, taking into account the capacity of the new generating facility,” – said the Agency.

From January 25 to put into operation the first stage of the Tauride and TES Balaklava (Sevastopol) – power units and all related infrastructure. The second unit of Balaklava TPP also successfully passed a comprehensive test, confirming stable working parameters. At the moment it undergoes final inspection of Rostekhnadzor. The total capacity of two power units of thermal power plants in Sevastopol is 500 MW.